Projects

8820

2014/04/15

 
1. BRIEF DAILY WORK ACTIVITIES DESCRIPTION QTY
1. Number of Workers 106
2. Number of Earthmoving Equipment 13
3. Number of Heavy Vehicles 21
4. Number of Special Equipment (Specify) Nil
 
2. WARNINGS
1. Vehicle crossings: Taxiway A 1, 2,3,4 and C
2. Blasting: Nil
3. Dust: Mitigated by watering
4. Other hazards (Specify) Occasional night work in progress see local NOTAM
 
3. CLOSURES
1. Planned Closures: Nil
2. Taxi ways: Nil
 
4. NAVIGATION AIDS
1. Operational: DME,NDB,VOR,AWOS
2. Not operational: N/A
3. Procedures in place: N/A
 
5. ADMINISTRATION
1. Please refer to:  
2. NOTAM
 
DATE NUMBER DESCRIPTION
140502 A1700/14 Const vehicles crossing TWY C
140516 A1845/14 Phase 3 of New Runway
140502 A1699/14 Const vehicles crossing east of threshold 25
3. AIP Supplement:
 
DATE NUMBER DESCRIPTION
     
 
6. PLANNED WORK FOR THE WEEK
1. Tarring from Nil from Nil
2. Pre Shaping from Chainage 2170 from Chainage 2400
3. Priming from Nil from Nil
4. Filling from Chainage 2350 from Chainage 2800
5. Top Soil Re-Hab from Chainage 800 from Chainage 1300
6. Procedures in place from Nil from Nil